Construction event - Casted closure segment of Sai Gon Bridge

Construction event: Casted closure segment of Sai Gon Bridge – is one of five special Bridge of metro line Ben Thanh – Suoi Tien (metro Line1) 

In the morning of September 30, 2016, Management authority for Urban railway of Ho Chi Minh City organisation for casted closure segment of Saigon Bridge,  ticking the milestone is important in the package 2 (Elevated & Depot) of the metro Ben Thanh - Suoi Tien.

To commence construction of Sai Gon Bridge started from December 2013 with technology of constructed by Free Cantilever Method (FCM), superstructure is box beam with three spans consecutive, the length of 267.5 m and width of 11,1m. Navigational clearance is corresponding to the Saigon Bridge 1&2 running parallel. Completed construction time was 33 months and ensures construction schedule was set out