Overall construction progress 2014

Overall cumulative actual progress by this year has reached 26.01%. The clearance of site hand over has been outstanding householder at Binh Duong province

At the Site, the Contractor implemented: Construction progress from Bason ship yard to link road of National University, continue the construction of the superstructure for viaducts, stations, special bridge:

-   Viaduct: Complated 1.699/2.626 pile; 248/431 pile cap; 199/431 columns; 75/431 pier cap.

-   Depot: Continue Earthworks, piling of retaining wall, drainage system. Completed 471/489M3 of earthworks; 504m of retaining wall; 240m of drainage system.

-  Station: Construction of bored pile; pile cap, column has completed at Thao Dien, Rach Chiec, High Tech Park, Phuoc Long, Binh Thai and Thu Duc station. Contractor is preparation construction of bored pile for Van Thanh station and PHC pile of some stations.

-  Special Bridge: Commencement of construction for Dien Bien Phu Bridge on February 2014 and for Van Thanh on June 2014. So far completed the bored piles, pile cap and column of Saigon Bridge; continue construction of pile cap for Dien Bien Phu and Van Thanh Bridges.

-  Casting yard: Working expeditiously prepare for casting girders work serving for launching girder in June 2015.

       Overview of construction after 2 years

Construction site of Van Thanh Bridge

Construction site of Van Thanh station

Construction site of viaduct (VD03)

Construction site of viaduct (VD05)

Construction site of Tan Cang station

Construction site of Saigon Bridge

Construction site of Viaduct (VD12)

Construction site of Rach Chiec station

Construction site of viaduct (VD13)

Construction site of Binh Thai station

Construction of pier cap

 

Construction site of Depot

Construction of drainage systerm at Depot

Casting yard