Overall construction progress update June.2015

 Overall cumulative actual progress to June 2016 has reached 56.25%, in wich design pakage basically completed 86%; construction of sub-structure completed 98% and throughout route is carrying out construction of superstructure.

 Construction achieved as follows:

  •  Viaduct: Total length 12.5 km

           Construction of sub-structure completed 98%

           Construction of superstructure: in with U-type girder installation completed 200/361 spans (approximately 7km), completed casting beams for 06 special spans connect to Binh Thai station and currently deployment casting beams for 24 special spans connect to An Phu station.

  •  Station: continue completing for construction of sub-structure of stations: Suoi Tien terminal, Van Thanh, Tan Cang. Completed and continue carrying out for construction of flatform and concourse level of stations: National University, An  Phu, Thu Đức and Hightech Park.  Stations: Thao Dien, Phuoc Long, Binh Thai and rach Chiec preparing for construction of finishing work.
  •  Special Bridge: there are 05 special Bridge under construction in wich: Sai Gon, Van Thanh, Rach Chiec and Dien Bien Phu are carrying for construction of superstructure. Ha Noi Highway Bridge is carrying for construction of sub-structure.
  •  Depot: concentrate on completing for construction of retaining walls and drainage system, implementation for construction of fencing walls and sub-structure of wagons repairing workshop and infrastructure repairing workshop.

 Overview of construction update in June 2016