Overall cumulative actual progress to June 2016 has reached 56.25%, in wich design pakage basically completed 86%; construction of sub-structure completed 98% and throughout route is carrying out construction of superstructure.
Construction achieved as follows:
- Viaduct: Total length 12.5 km
Construction of sub-structure completed 98%
Construction of superstructure: in with U-type girder installation completed 200/361 spans (approximately 7km), completed casting beams for 06 special spans connect to Binh Thai station and currently deployment casting beams for 24 special spans connect to An Phu station.
- Station: continue completing for construction of sub-structure of stations: Suoi Tien terminal, Van Thanh, Tan Cang. Completed and continue carrying out for construction of flatform and concourse level of stations: National University, An Phu, Thu Đức and Hightech Park. Stations: Thao Dien, Phuoc Long, Binh Thai and rach Chiec preparing for construction of finishing work.
- Special Bridge: there are 05 special Bridge under construction in wich: Sai Gon, Van Thanh, Rach Chiec and Dien Bien Phu are carrying for construction of superstructure. Ha Noi Highway Bridge is carrying for construction of sub-structure.
- Depot: concentrate on completing for construction of retaining walls and drainage system, implementation for construction of fencing walls and sub-structure of wagons repairing workshop and infrastructure repairing workshop.
Overview of construction update in June 2016