Overall cumulative actual progress to December 2016 has reached 66.63%, in which design pakage basically completed 98%; construction of sub-structure completed 100% and the construction of superstructure for viaduct by PSM have been completed 98%. At present, the construction of superstructure for remaining special bridges is continuing, as well as viaduct by FCM. The terminal is carrying out the M&E systems, preparation of finishing works and steel roof structure. It is expected that by the end of 2018, the package 2 will be completed.
Construction achieved as follows
Construction of sub-structure completed 100%
Construction of superstructure: in whith 12,0km U-type girder installation completed 313/361 spans (approximately 10,5km).
Images of viaduct construction at the site
roof structure.
Images of station construction at the site
Sai Gon Bridge: complete and casted closure segment dated 30th September 2016
Văn Thanh Bridge: complete and casted closure segment on March 2017
Rach Chiec Bridge: expected to complete and casted closure segment on Sep.2017
Other special Bridge: Dien Bien Phu and HNHW are under construction of superstructure.