Overall construction progress update December/2015

Overall cumulative actual progress to December 2015 has reached 47.56%.  Construction of Package 2 basically completed 85% of sub-structure and carrying out construction of superstructure for viaduct segments, special Bridge and Station (included 17 viaduct segments, 05 special Bridge and 11 stations)

Construction achieved as follows:

  •    Viaduct: The construction of substructure has completed 85% progress:

            + Bored pile: completed 96%

            + Pile cap: completed 88%

            + Column: completed 81%

            + Pier cap: completed 67%

            + Construction of superstructure: by launching girger work and girger installation completed 87 spans (approximately 3km)

  • Station: Continue to complete for construction of substructure of stations: Suoi Tien terminal, Van Thanh, Tan Cang, National University, An Phu. Carrying out for construction of concourse level of stations: Thao Dien, Phuoc Long, Binh Thai, Thu Duc and construction of platform level of Hightech Park station.
  • Special Bridge: there are 05 special Bridge under construction:

           + Sai Gon Bridge: construction of substructute has completed, now is carrying falsework of lateral span.

           + Rach Chiec Bridge: completed 3/4 pile cap, 3/4 column and 1/4 pier cap.  

           + Dien Bien Phu Bridge: completed 5/5 column and 1/4 pier cap.

           + Van Thanh Bridge: completed 3/4 pile cap and 2/4 column.   

           + Ha Noi Highway: completed 2/2 pile cap and 2/2 column

  •   Depot: concentrate on completing for construction of retaining walls and drainage system, PHC piling for wagons repair workshop and infrastructure repair workshop.
  •  Casting yard: casting segment completed 1.446/4.563 (about 32%) typical U girder.

Significant Events during the Period: On 18th December 2015: The first bored pile at Suoi Tien terminal

 Overview of construction update in December 2015