Special events of construction stage is commencement for the next items of viaduct, special Bridge and stations with details:

  • 19 February 2014 : Casted 1st bored pile at Rach Chiec station.
  • 25 February 2014 : Casted 1st bored pile at VD14 site.
  • 06 March 2014 : Casted 1st bored pile DBP1-03 at Dien Bien Phu bridge.
  • 06 April 2014 : Casting 1st bored pile at VD03.
  • 10 May 2014 : Casting 1st bored pile at An Phu Station.
  • 26 June 2014 : Casting 1st pile cap at High Tech Park Station.
  • 30 July 2014 : Casting 1st pile cap at Thao Dien Station.
  • 31 July 2014 : Casting 1st Bored pile cap at VD15.
  • 16 August 2014 : Casting 1st pier cap at VD7.
  • 19 August 2014 : Casting 1st bored pile at Van Thanh Bridge.
  • 23 August 2014 : Casting 1st pile cap at Sai Gon Bridge.
  • 28 August 2014 : Casting 1st bored pile at VD2.
  • 1 August 2014 : Casting 1st pile cap at Phuoc Long Station.
  • 14 August 2014 : Casting 1st pile cap at Binh Thai Station.
  • 30 August 2014 : Casting 1st pile cap at Thu Duc Station.
  • 05 September 2014 : Casting 1st pile cap at Rach Chiec Station.
  • 14 September 2014 : Casting 1st Bottom Pier SG2 at Sai Gon bridge.
  • 17 September 2014 : Casting 1st pile cap DBP2 at Dien Bien Phu bridge.
  • 19 September 2014 : Casting 1st Bored pile at Tan Cang Station.
  • 27 September 2014 : Casting 1st pier column at High Tech Park Station.
  • 07 October 2014 : Casting 1st pier column at Binh Thai station.
  • 10 October 2014 : Casting 1st bored pile at VD05.
  • 13 October 2014 : Casting 1st pier column at Phuoc Long station.
  • 16 October 2014 : Casting 1st Pier cap at VD11.
  • 03 November 2014 : Casting 1st Bored pile at Suoi Tien Station.
  • 13 November 2014 : Casting 1st Pier cap at VD06.
  • 15 November 2014 : Casting 1st Pier cap at VD13.
  • 18 November 2014 : Casting 1st Pier column at VD03.
  • 06 December 2014 : Casting 1st Pier column at VD15