Hotline:
0937 500 300

Construction events

Mileston events of the construction - 2014

Mileston events of the construction - 2014 (22/01/2016)

Special events of construction stage is commencement for the next items of viaduct, special Bridge and stations with details: 19 February 2014 : Casted 1st bored pile at Rach Chiec station. 25 February 2014 : Casted 1st bored pile at VD14 site. 06 March 2014 : Casted 1st bored pile DBP1-03 at Dien Bien Phu bridge. 06 April 2014 : Casting 1st bored pile at VD03. 10 May 2014 : Casting 1st...
Milestone events of the construction - 2013

Milestone events of the construction - 2013 (12/10/2015)

- April 2013 : Contractor has begun installation of fence along the  Hanoi Highway and implementing  construction of bored pile  work for  structure of viaducts and stations  - December 2013:To commence construction of Saigon bridge Saigon Bridge is one of five special bridges of the project, with the length of 267.5 m and is constructed by Free...