Overall construction progress

Ground breaking date of Contract Package 2 was performed on 28th August, 2012. Package 2 is one of packages of the project first implemented, Expected time to complete of contract Package on December 2017.

Overall construction progress update to march 2017

Overall construction progress update to march 2017 (12/09/2017)

Overall cumulative actual progress to December 2016 has reached 66.63%, in which design pakage basically completed 98%; construction of sub-structure completed 100% and the construction of superstructure for viaduct by PSM have been completed 98%. At present, the construction of superstructure for remaining special bridges is continuing, as well as viaduct by FCM. The terminal is carrying out the...
Overall construction progress update to December 2016

Overall construction progress update to December 2016 (02/06/2017)

Overall cumulative actual progress to December 2016 has reached 63.97%, in which design pakage basically completed 97%; construction of sub-structure completed 100% and on throughout all package 2 is carrying out construction of superstructure and preparing for finish work of stations.   Construction achieved as follows  1. Viaduct: Total length 12.5 km   Construction...
Overall construction progress update September 2016

Overall construction progress update September 2016 (31/10/2016)

Overall cumulative actual progress to Septemebr 2016 has reached 56.25%, in which design pakage basically completed 96%; construction of sub-structure completed 98% and on throughout all package 2 is carrying out construction of superstructure.  Construction achieved as follows:  1) Viaduct: Total length 12.5 km  Construction of sub-structure completed...
Overall construction progress update June.2015

Overall construction progress update June.2015 (20/07/2016)

 Overall cumulative actual progress to June 2016 has reached 56.25%, in wich design pakage basically completed 86%; construction of sub-structure completed 98% and throughout route is carrying out construction of superstructure.  Construction achieved as follows:  Viaduct: Total length 12.5 km            Construction of sub-structure completed...
Overall construction progress update December/2015

Overall construction progress update December/2015 (15/02/2016)

Overall cumulative actual progress to December 2015 has reached 47.56%.  Construction of Package 2 basically completed 85% of sub-structure and carrying out construction of superstructure for viaduct segments, special Bridge and Station (included 17 viaduct segments, 05 special Bridge and 11 stations) Construction achieved as follows:    Viaduct: The construction of...
Overall construction progress update Sep.2015

Overall construction progress update Sep.2015 (25/01/2016)

Overall cumulative actual progress by this month has reached 42.85%. Hand over for site construction completed 100%. So far there is some construction areas progress delayed by problems of utility has not been greed relocation. Overall of site construction: Continue to implement of construction section from Bason shipyard to Depot.         Viaduct: The construction...
Overall construction progress update June/2015

Overall construction progress update June/2015 (26/10/2015)

Overall cumulative actual progress by this year has reached 37.34%. The exists clearance of site in Binh Duong province has completed on March 2015. At the Site, the Contractor implemented: Continue construction progress section from Bason Shipyard to Depot. To accelerate the substructure construction of viaducts and stations section from Saigon Bridge to intersection of National University...
Overall construction progress 2014

Overall construction progress 2014 (20/10/2015)

Overall cumulative actual progress by this year has reached 26.01%. The clearance of site hand over has been outstanding householder at Binh Duong province At the Site, the Contractor implemented: Construction progress from Bason ship yard to link road of National University, continue the construction of the superstructure for viaducts, stations, special bridge: -   Viaduct: Complated...
Overall construction progress 2013

Overall construction progress 2013 (19/10/2015)

  - Overall cumulative actual progress by this year has reached 10.73%. In which completed for site construction hand over about 90%, completed the geological survey and topography 97%, 100% pile load test completed     - In 2013 The contractor construction of bored pile (section from Saigon bridge to Base II Thu Duc intersection) and Depot area. - Since April.2013,  the...