Overall construction progress update to December 2016

Overall cumulative actual progress to December 2016 has reached 63.97%, in which design pakage basically completed 97%; construction of sub-structure completed 100% and on throughout all package 2 is carrying out construction of superstructure and preparing for finish work of stations.

  Construction achieved as follows

 1. Viaduct: Total length 12.5 km


Construction of sub-structure completed 100%


Construction of superstructure: in whith 12,0km U-type girder installation completed 313/361 spans (approximately 10,5km), completed casting beams for spans connection to Binh Thai station and currently is carrying out for casting beams by FSM method for remaining of viaduct section.


Images of viaduct construction at the site

2. Station:

Continue complating for construction of concourse level of stations. The preparing for finishing work and steel roof of stations : Thao Dien, Phuoc Long and Binh Thai.


Images of station construction at the site

Van Thanh station

Tan Cang Station

Thao Dien station

An Phu station

Rach Chiec station

Phuoc Long station

Binh Thai Station

Thu Duc station

National University station

Suoi Tien Staion

HTP station

3. Special Bridge: There are 05 special Bridge under construction in which:


Sai Gon Bridge: complete and casted closure segment on date 30th September 2016


Other special Bridge: Van Thanh, Rach Chiec and Dien Bien Phu are under construction of superstructure, and expected time for complete and casted closure segment of Van Thanh Bridge on February 2017.


Ha Noi Highway Bridge completed for construction of sub-structure, and preparing for construction of superstructure.


Images of special bridge construction at the site

Van Thanh bridge

DBP Bridge

Sai Gon Bridge

Rach Chiec Bridge

4. Depot: concentration completing for construction of retaining walls and drainage system, implementation for construction of fencing walls and sub-structure of wagons repairing workshop, infrastructure repairing workshop and main workshop.

     Images of Depot construction at the site