Overall construction progress update September 2016

Overall cumulative actual progress to Septemebr 2016 has reached 56.25%, in which design pakage basically completed 96%; construction of sub-structure completed 98% and on throughout all package 2 is carrying out construction of superstructure. 

Construction achieved as follows:

 1) Viaduct: Total length 12.5 km

 Construction of sub-structure completed 98%.

 Construction of superstructure: in whith U-type girder installation completed 200/361 spans (approximately 7km), completed casting beams for 06 spans connection to Binh Thai station and currently is carrying out for casting beams by FSM method at VD04, VD07, and VD17.

 Images of viaduct construction at the site

 

 Sub- structure of viaduct

 

 

Complated for erection girder of viaduct

Viaduct section at district 02 

2) Station: 

Continue completing for construction of sub-structure of stations: Suoi Tien terminal, Van Thanh, Tan Cang.

Completed and continue carrying out for construction of flatform and concourse level of stations: National University, An Phu, Thu Đức and Hightech Park.

Stations: Thao Dien, Phuoc Long, Binh Thai and Rach Chiec preparing for finishing work.

 Images of station construction at the site

 3) Special Bridge

There are 05 special Bridge under construction in which:

Sai Gon Bridge: complete and casted closure segment on date 30th September 2016

Other special Bridge: Van Thanh, Rach Chiec and Dien Bien Phu are under construction of superstructure. Ha Noi Highway Bridge is carrying for construction of sub-structure.

 Images of special bridge construction at the site

 

Sai Gon Bridge

Casted closure segment of Sai Gon Bridge

4) Depot

Cconcentration completing for construction of retaining walls and drainage system, implementation for construction of fencing walls and sub-structure of wagons repairing workshop, infrastructure repairing workshop and main workshop.

 Images of Depot construction at the site